CHAPTER 16 Aggregate Sales and Operations Planning

 

1.  A capacity plan is necessary to meet demand.

 

2.  Business plan influences capacity planning.

 

3.  Variation of product (or service) offering makes capacity planning more difficult.

 

4.  Both demand forecasts and capacity plans are necessary to produce the M.P.S.

 

5.  Revisions may be required before the MPS is finalized.

 

Shut down Point:  At this level of operations production cannot be economically justified.  (MR = MC below AVC—cost more to produce than not to produce at all.  This is the Shut down point)   

 

Key:  adjust capacity or demand or both to balance.  Shift demand--create new demand.

 

Basically, we attempt to do:

       1. adjust capacity (Reactive)

       2. alter demand pattern  (Aggressive)

       3. some of both

 

If you don't plan for changes in adjustable capacity in advance they cannot be changed--at least not efficiently.                       

 

Aggregate Planning--the process of looking at demand forecast for the intermediate horizon (MR planning) and establishing general plans about how the firm will utilize available resources within that time frame.

 

We are bound by Fixed Capacity which refers to those factor inputs that cannot be changed economically in the intermediate horizon.  Fixed capacity thus limits our options.

 

Capacity--Influences Price/Quality/availability and thus our ability to compete.  The highest sustainable level of output which can be achieved with current product specifications, product mix, worker effort, plant and equipment.  (It then must be an average.)

 

(Major Constraints--manpower, facility (plant), equipment, financing)

 

We wish to develop a plan that balances our capacity with demand.  We desire a plan that is:

 

1.  Feasible--it is a planned level of resource use that does not exceed our capacity.

 

2.  Optimal--best we can hope to do given our constraints and our goals.  Efficient and effective.

 

Purpose Best (feasible & optimal) prod. plan that balances expected demand and supply.   

 

The time frame for aggregate planning is usually 3 to 18 months.  It is a continuous process—updated monthly, weekly, quarterly.

 

18 months

 

1      Aggregate plan      18

  2       Revised A.P.          19

    3         Revised A.P.           20

 

The time frame must be long enough to allow elements of the aggregate plan to be changed.

 

Ex.   a.  labor

       b.  inventory levels

       c.  plans for   subcontracting

        d.  lead time to produce outputs

        e.  backorders

 

Alternative strategies for meeting seasonal demand

 

Pure Strategy--company plans to change only one variable to adjust to changes in demand.  (Labor, Inventories, Subcontracting, Production rate)

 

Mixed Strategy--changing a combination of variables.  (Hybrid)

 

Inputs

1.  Hours worked per week

2.  size of work force

3.  number of shifts

4.  extent of subcontracting

5.  inventory policies

6.  demand shifting strategies

7.  back order policies

 

**The capacity plan places an upward bounds on the M.P.S.

(can't produce level of output that exceeds capacity)

 

**NOTE:  The plan does not always = Demand for a period(s).

 

We would like to have adequate capacity to meet demand--not too much because idle resources cost money; and not to little because if we cannot meet customer demand they may go elsewhere.

 

Question:  How much capacity do we need?  Aggregate planning (adjustable capacity planning--effective capacity is set by aggregate plan) helps us to answer that question.

 

Approaches to Aggregate Planning

(Resource Requirements Planning or Rough-cut capacity planning)

 

1.  Bottom-up--you generally use a MRP system to develop plans for major products, or product families; then you consolidate those plans into one plan and evaluate the impact on company capacity.

 

We evaluate the resulting plan as follows:

 

a.  Is it feasible?  yes

 

       then ask

 

b.  Is it optimal?   Yes

 

Then: DO IT!

 

Else:  If it is not feasible--revise plans and redo.

 

Else if: If it is not optimal--revise plans and return to question 1 again.

 

2.  Top-down--develop an overall or aggregate rate of production (capacity).  (Often makes use of a pseudo product).

 

Then you disaggregate.

 

Assumption:  If total capacity is adequate then the right amount of capacity for all of the parts is available.

 

Trial & Error Approach is most common way of evaluating alternative courses of action relating to meeting market demand with capacity.  (Cost is normally an important factor in our choice.)


Aggregate (Capacity) Planning

 

1.  Bottom up

 

Used with MRP System

 

Developed tentative MPS for future periods based on families of products

 

Use rough cut capacity planning to evaluate load in relation to capacity and make adjustments as necessary to come up with capacity plan that is:

      

       Feasible--objective

 

       Optimal--subjective

 

(Fast Growing)

 

 

2.  Top down

 

Develop overall or aggregate rate of production using Pseudo product.

 

*Assumption:  capacity adequate for whole => capacity adequate for the parts.

 

a.  Subjective evaluation of goodness of plan.

 

Trial & Error --evaluates alternative ways of using resources to provide capacity necessary to meet demand.

 

(Cost often major selection criteria)

 

 

b.  Objective

 

evaluation of goodness of plan

 

Quantitative tools to determine optimal solution.

 

1.  Linear programming

 

2.  Linear Decision Rule (LDR)

 

       3.  Search Decision Rule

    (Computerized trial and error approach)

 

 

SERVICES

 

Aggregate planning for services is not much different, except for that there is not inventory for adjustment and backordering may not be practical as they will just use a competitor.

 

Yield Management—process of allocating the right type of capacity to the right type of customer at the right price and time to maximize revenue or yield.

       Conditions for Effective use of Yield Management:

 

1.         Demand can be segmented by customer

2.         Fixed Costs are high and Variable Costs are low

3.         Inventory is perishable (service cannot be stored)

4.         Product can be sold in advance

5.         Demand is highly variable

 

Essence of Yield Management in managing Demand through control of pricing and duration of service.  See Model p. 578.

 

Ex. Price—lower price for flying certain times.

Ex. Duration—Special conference rates at hotel apply only to conference period of 4 days.